ACTION: s SCREEN: SUSF
USERID: AFNS FUNCTION:
change ORG:
D O C U M E N T S U S P E N S E
S
BATCH DOCUMENT
PROCESS E ----------------
----------------------
LAST LAST DATE
L TYPE AGCY NUMBER TYPE AGCY NUMBER STAT APPRV DATE
USER (YYMMDD) - ---- ---- ------ ---- ---- ------------
----- ----- ------ -------- --------
x . . .
PVQ 010 50102000351 SCHED 00000 040930 AFNS 041001 .
. . PVQ 010 50102000352 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000353 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000354 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000355 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000356 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000357 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000358 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000359 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000360 REJCT 00000 040930 AFNS .
. . PVQ 010 50102000361 REJCT 00000 040930 AFNS
¨
To schedule a document to process on a
future date, key S in the ACTION, “change” in the FUNCTION, and a X in the
SELECTION field of the document to be processed sometime in the future. Next, key in the future processing date in
the Process Date (YYMMDD) field and
press ENTER. The above screen illustrates that the
document will be processed on
¨
Transactions will be held in suspense
until the processing date is reached.
¨
Putting the document on hold will
override the process date.
¨
The document will not process until it
is taken off hold.
¨
To remove the future processing date,
change the date to the current date.
¨ Future processing will only work on documents that have a scheduled status. For example, if a document has a status of held or rejected, the system will not process the document due to it being held or rejected with errors. Any errors must be corrected and an edit must be performed before changing the process date field.